Construction of a self-service car wash starts from preparation and filling of the site.

SUBJECT TO AVAILABILITY OF NECESSARY UTILITIES, THE NEXT STAGES ARE:
  • preparation of the bedding of slabs with underfloor heating;
  • installation of treatment facilities;
  • pouring the slabs;
  • erection of the structure, metal frame, advertising friezes, roof/shed;
  • installation of video surveillance;
  • site improvement (asphalt paving, lighting, landscaping, recreation area, etc.).

The correct sequence of construction works will help you correctly allocate time and financial resources.

ZERO STAGE – PLUMBING AND OUTDOOR SEWERAGE:

  • installation of the hoarding,
  • digging with an excavator to make settling wells,
  • installation of well rings on the sand-and-gravel base,
  • waterproofing of wells,
  • laying of wastewater and water supply pipes,
  • laying the electric cable under the slab.

ZERO STAGE – TREATMENT FACILITIES AND REINFORCED CONCRETE STRUCTURES:

  • sand-and-gravel base,
  • laying ANTIFROST pipes,
  • protective film and heat insulation,
  • removable/stay-in-place formwork,
  • laying of two-level bars and pits at washing stations,
  • laying pipes for underfloor heating,
  • pouring concrete M350,
  • surface grinding and surface coating.

CONSTRUCTION OF THE SERVICE ROOM:

  • assembly of the frame of the service room from galvanized metal,
  • sheathing with sandwich panels or other materials,
  • installation of doors and windows, ventilation,
  • installation of plumbing.

CONSTRUCTION OF WASHING STATIONS AND ELECTRICAL EQUIPMENT:

  • installation of metal structures for washing stations and frieze,
  • installation of a shed/roof and inter-station partitions,
  • installation of electrics of a car wash and lighting of the territory,
  • removal of the hoarding.

FINAL STAGE OF THE CONSTRUCTION:

  • improvement of the area of a car wash,
  • installation of video surveillance and security systems,
  • installation of navigation (road signs, traffic lights, signs) on the territory of a car wash.

NEXT STAGES:

  • installation of washing equipment,
  • installation of equipment for wastewater treatment,
  • creation of conditions for work of the service staff.

For putting the facility into operation as soon as possible after completion of construction, use the advice of ALLES specialists. At the time of launch, the advice and support of professionals is just as important as during the preparation process. The experience of successful launches accumulated by the company will allow a smart car wash to reach payback as quickly as possible.

A FEW MORE USEFUL BASICS OF BUILDING A SELF-SERVICE CAR WASH:

High-quality treatment facilities that not only remove suspended solids, oil sludge and other suspensions, but also by means of chemicals neutralize surface-active agents, phosphates and other harmful substances present in water (cleaning "for appearance's sake" not only harms the environment, but can also result in high fines);

Smooth sanded floor with a slope of 3-4 degrees to the center of a washing station, where there is a drain hole for quick water drainage and optimization of labor costs for cleaning;

High partitions (not less than 3 m) resting on the floor to avoid drenching clients from above and splashing on their feet from neighboring boxes;

Bright lighting on the territory and at washing stations, so that car drivers feel comfortable visiting a car wash even at night;

Improvement means convenient entry/exit, smooth space paved with asphalt or setts with proper lighting, recreation and waiting area, a WC, waste bins – all of this will become the undeniable advantages of your car wash.